Site Progress Report

Information about Site Progress Report

Published on December 23, 2009

Author: pyamod

Source: authorstream.com

Content

Slide 1: Project : SITE PROGRESS REPORT Developer : Consultant: Contractor : Munich Millennium Tower PYAMOD Emaret Al Sharq Architecture Consultants MNG Zemtas Soil & Foundation Engineering Location : Dubai Silicon Oasis Date : December 20, 2009 CURRENT ACTIVITIES: Casting of left side shoring piles are complete NEXT ACTIVITY: Capping beam of the shoring piles PROJECT DETAIL: Casting of right side (last side) shoring piles have started (Anticipated finish date: January 8th, 2009)